Large Telecommunications Company
Project Information
Client: Large Telecomms Company
Value: ZAR 4.4M
Duration: 12 Months
Role: Programme management, project management, cost consultancy, Strategy Alignment
Key Objectives and Deliverables
- To ensure energy efficiencies through accurate usage, billing and tariff optimization
- To Reduce minimize Energy Costs
- To enhance continual improvement program
- To determine a consistent metric for Baselining and benchmarking
- To establish a strategy for adjusting and optimizing energy through systems and procedures
Overall Project Outcome
- The completion of AMR systems at the 50 high usage sites that constitute almost 20% of total consumption across all Large Telecommunications Company sites.
- Tariff optimisation of 40% of the sites that resulted in savings of over 6% of the total bill per annum.
- Power Factor correction at 10 sites to provide energy savings of 3%.
- Baseline and Benchmarking metric set for efficient management of usage and optimisation.
- Integration into Archibus for Site owners and Facility mangers to optimise and mange sites effectively.